Idaho anchors the investment case
The central question in Centry's analysis is whether Oklo can turn its technical progress into a commercial power business. Its first commercial reactor, the 75-megawatt Aurora unit in Idaho, now has concrete and steel in place and has passed three of five safety approvals, according to the firm. But the expected startup has shifted from 2028 to a window spanning 2028 and 2029.
A separate test reactor is already operating. Groves-1, in Lockhart, Texas, received Department of Energy startup authorization on July 23, 2026, and first sustained a nuclear reaction on August 5. The DOE subsequently authorized continued research and training at the facility.
Oklo's third-quarter filing identifies DOE authorization as the primary route for the Idaho plant, while retaining the option of Nuclear Regulatory Commission licensing. It records NRC approval of the Principal Design Criteria report in April 2026 and approval of the Preliminary Documented Safety Analysis in June. Centry also notes that regulators now allow results from government-authorized test reactors to support commercial licensing.
Cash provides time, but not a fleet
Oklo ended September with $3.1 billion in cash and securities, after selling $2.3 billion in new shares during 2026. Centry estimates that balance represents roughly $16 for each share trading near $21.
Against 2026 spending of $120 million to $150 million on operations and $400 million to $500 million on construction, the firm estimates about five years of cash runway. In its assessment, that should be enough to bring Idaho into operation, but not enough to finance a fleet of plants. After subtracting cash, Centry puts the market's valuation of the rest of Oklo's business at about $1 billion.
Its valuation uses two outcomes. Centry assigns about a 35% probability to the Idaho plant operating and the Ohio agreement becoming binding; in that case, it estimates a value near $65 per share after further dilution. In the failure scenario, it estimates remaining cash of about $8 per share. The weighted result is approximately $28, with the analysis page listing $28.61 against a share price of $20.77. Centry describes that estimate as roughly one-third above the market price and about half the $55 average Wall Street target.
Meta's Ohio plans still need a binding commitment
The Ohio project is a major condition of Centry's higher-value scenario. Announced in January 2026, Oklo's agreement with Meta calls for a 1.2 GW nuclear campus in Pike County to supply the company's regional data centers. Oklo owns the 206-acre property, which previously belonged to the DOE.
The schedule calls for pre-construction work and site characterization to begin in 2026. The first phase could enter service as early as 2030, followed by staged expansion toward 1.2 GW by 2034. Centry cautions that the agreement is not yet binding and says construction would require outside financing or additional share sales.
Meta's January procurement also included TerraPower and Vistra. The three agreements together support up to 6.6 GW of new and existing clean energy by 2035, tied to Meta's Prometheus AI data center in New Albany, Ohio.
Another proposed power project suffered a regulatory setback in September, when regulators declined to reinstate a Virginia development that the regional grid operator had removed from its review process. Nuclear accounted for just 150 megawatts of the proposed 750-megawatt project; fuel cells and natural gas made up the balance. Centry interprets that mix as a possible strategy of supplying power before adding reactors, potentially allowing power revenue before Oklo's first reactor begins commercial operation.
Fuel contracts and a recycling strategy
Oklo intends to retain ownership of its plants and earn revenue from electricity sales, rather than follow the reactor-design-and-sales model Centry attributes to most nuclear startups. Its fast-reactor technology can use recycled nuclear fuel and draws on the Experimental Breeder Reactor-II, which supplied electricity to the grid and recycled its own waste for more than 30 years. Recovered fuel from that reactor is now being recycled for Oklo's first commercial plant.
Centry sees a potential fuel source in material otherwise treated as waste, provided recycling can work at scale. Alongside that effort, Oklo has arranged multiyear fuel supplies from Centrus Energy and reserved heavy steel components for 27 reactor units scheduled between 2030 and 2035.
The November 11, 2026, agreement between subsidiary Oklo Power SODI and Centrus requires purchases of specified enrichment quantities for delivery in 2029 through 2031 on a take-or-pay basis. Oklo must also make two advance payments totaling $35 million. The agreement specifies uranium enriched to 19.75% and remains in effect until December 31, 2039, or completion of both parties' obligations, whichever comes later.
Centrus says the Oklo contracts bring its customer contracts and purchase commitments for low-enriched uranium and high-assay low-enriched uranium to $5.4 billion. Those commitments concern new enrichment capacity that has not yet been built.
An AI-linked stock in a developing industry
Oklo's market profile grew from its ties to Sam Altman and demand for dependable, clean electricity for AI data centers. Altman met MIT-trained founders Jake DeWitte and Caroline Cochran in 2013, recruited Oklo to Y Combinator in 2014, and invested in 2015, becoming chairman. The founders were pursuing small reactors capable of using recycled fuel. Oklo reached the NYSE in May 2024 through a merger with Altman's blank-check company, and its shares later exceeded $115.
Other developers have also reached technical and financing milestones. TerraPower, another Meta nuclear partner, received the NRC's first modern commercial fast-reactor construction permit in March 2026 for its 345 MWe Natrium sodium-cooled reactor in Kemmerer, Wyoming. Nuclear construction began April 23.
At X-energy, the TRISO-X subsidiary holds the first NRC Part 70 license for HALEU fuel fabrication. Amazon anchored a financing round of roughly $700 million aimed at more than 5 GW of Xe-100 projects.
Oklo has expanded its own capabilities through acquisitions. In June 2026, it bought ARMEC, LLC, whose precision manufacturing and mechanical engineering work includes high-precision machining and nuclear-industry prototyping, and Creative Engineers, Inc., which specializes in chemical process engineering for sodium and alkali-metal systems. Combined consideration was about $33.4 million.
The company reported $1.86 million in revenue for the quarter ended September 30, 2026, primarily from engineering, consulting, manufacturing and fabrication services. Its net loss for the period was $41.7 million.
The next tests
Centry identifies three main threats to its investment case: delays in Idaho's remaining safety reviews, Meta withdrawing from Ohio, and continued share issuance at current prices. Over the following year, it plans to watch for reactor-component installation in Idaho, progress toward the first complete fuel assembly targeted for 2027, and a binding Ohio commitment.